      1. 3.2.1 Network Exploitation and Grid Asset Consolidation
      2. 3.2.2 Connection
      3. 3.2.3 Electricity Transmission
      4. 3.2.4 Additional (non-tariff) services
      5. 3.2.5 Consumer liaison
      6. 3.2.6 Key RAS metrics
      7. 3.2.7 Key IFRS metrics
      8. 3.2.8 Tariff Policy
      9. 3.2.9 Investments
      10. 3.2.10 Innovations
      11. 3.2.11 Progress of the Digital Transformation Program

For the operation of the site, we collect cookies, information about the IP address and location of users. If you do not want this data to be processed, please leave the site.

3.2.1 Network Exploitation and Grid Asset Consolidation

Network exploitation

Indicator 2022 2023 2024 2024/2023, %
Substations, pcs 38,141 38,658 41,690 +7.8%
Substation capacity, MVA thousand 34.9 35.3 37.4 +6.0%
Power lines (circuits), km 153,398 154,113 161,841 +5.0%

Repairs in 2022-2024

The Company’s repair and maintenance target for 2024 totaled RUBruble 6,513 million, real expenses in 2024 totaled RUBruble 7,276 million or 112%.

The 2024 repair program (branch breakdown) , RUBruble million

Branch Target Actual % of completion
Permenergo 2,381 2,539 107%
Sverdlovenergo 2,259 2,420 107%
Chelyabenergo 1,855 2,297 124%
Rosseti Ural (incl. HQheadquarters) 6,513 7,276 112%

The overrun was mainly due to recovery and unscheduled works. Total costs of the branches spent on outsourcing repair works totaled RUBruble 1,166 million or 16%, with RUBruble 6,110 million or 84% spent on in-house repair works.

The Company’s repair program in 2022-2024

Type of repair MU 2022 real values 2023 real values 2024 target values 2024 real values 2024 % of completion
Power line corridor clearing ha 10,387 11,128 10,064 10,415 103%
Groundwire replacement km 258 231 248 266 107%
Insulator replacement pcs 111,431 113,342 96,461 111,103 115%
Transformer overhaul pcs 44 29 28 38 136%
Switch overhaul pcs 1,605 1,368 1,350 1,445 107%
Overhaul of isolating switches, short circuitors, disconnecting switches pcs 1,838 1,835 1,582 1,597 101%
Total repair costs RUBruble million 4,829 6,185 6,513 7,276 112%

The overrun was mainly due to recovery and unscheduled works. The repair program for 2025 totals RUBruble 7,187 million or -1.2%YoY, with RUBruble 5,966 million or 83% to be spent on in-house works and RUBruble 1,221 million or 17% to be spent on outsourcing works.

Description of incidents on network facilities in 2022-2024

The number of incidents on 110kV+ networks of the Company’s branches decreased 5.2% on 2023 and decreased 4.8% on 2022. The diagram shows the amount of incidents and disturbances on 110kV+ networks.

Incidents on 110 kV+networks, pcs

 

Factors of incidents

Primary factors of incidents on 110kV+ networks in 2024 are natural impacts, external impacts, aging of equipment, exploitation defects. In 2024, all branches of the Company achieved long-term reliability targets, set by the regional regulators, incl. with allowances made for permissible variation coefficient of 30%, stipulated by the Guidelines[18]. Sverdlovenergo failed to complete Isaifi LV, with total Isaidi and Isaifi completed.

Reliability target and real values of our branches

Download

Branch

Permenergo

Chelyabenergo

Target value Real value ∆,% Target value Real value ∆,%
Isaidi, hours 0.7259 0.6224 -14.3% 0.9787 1.0998 12.4%
Isaifi, pcs 0.6866 0.6068 -11.6% 0.7774 0.7901 1.6%

Download

Indicator

Sverdlovenergo

Target value Real value ∆,%
Isaidi HV, hours 0.8317 0.0446 -94.6%
Isaidi MV1, hours 0.7023 0.1752 -75.1%
Isaidi MV2, hours 2.3515 1.6297 -30.7%
Isaidi LV, hours 2.6417 2.8515 7.9%
Isaifi HV, pcs 0.1229 0.04340 -64.7%
Isaifi MV1, pcs 0.3106 0.0709 -77.2%
Isaifi MV2, pcs 0.7795 0.6563 -15.8%
Isaifi LV, pcs 0.9630 1.3170 36.8%

In 2024, to enforce reliable grid performance, the Company has approved a set of special-purpose programs on technical development[19], incl.: programs on reduction of incident rate and enhancement of equipment reliability; maintenance and repairs; exploitation works; upgrade (retrofitting) of grid facilities; enhancement of fire safety; equipment of special-purpose vehicles and transport with state-of-the-art security tools; purchases of electric supply reserves, etc. The primary expected effect from the above-mentioned and investment programs lies in the control of the level of incident rates and creation of conditions for achieving the reliability targets set by the regulators.

Consolidation of grid assets

PAOPublic Joint-Stock Company Rosseti Ural (jointly with AOJoint-Stock Company EESK) consolidates grid assets to shape a unified network area on the territory of the Company’s operations helping create a single point of responsibility for reliable and high-quality electricity supply and providing additional possibility to connect new consumers to the consolidated networks.

Consolidation of grid assets

Download

Asset type

2022

2023

2024

MVA Kmkilometer c.u.conventional units MVA Kmkilometer c.u.conventional units MVA Kmkilometer c.u.conventional units
Rosseti Ural’s total 2,900 5,737 46,834 4,396 10,727 79,802 4,582 7,826 69,895
Acquisition of grid facilities 56 358 1,721 1,023 4,940 27,414 40 14 466
Rented grid facilities 2,824 5,221 44,632 3,225 4,756 48,244 3,638 4,478 49,669
Other (permanent rights of ownership and use) 13 82 274 118 741 3,267 34 185 784
Other (temporary rights of ownership and use) 7 76 207 30 290 877 870 3,149 18,976
AOJoint-Stock Company EESK’ total 1,266 9,356 31,317 579 1,596 9,920 555 1,495 9,632
Acquisition of grid facilities 0 0 12 82 0 121 8 0 74
Rented grid facilities 1,247 9,356 31,078 443 1,358 8,343 524 1,399 9,087
Other (permanent rights of ownership and use) 19 0 227 54 238 1,456 23 96 471
Other (temporary rights of ownership and use) 0 0 0 0 0 0 0 0 0