      1. 3.2.1 Network Exploitation and Grid Asset Consolidation
      2. 3.2.2 Connection
      3. 3.2.3 Electricity Transmission
      4. 3.2.4 Additional (non-tariff) services
      5. 3.2.5 Consumer liaison
      6. 3.2.6 Key RAS metrics
      7. 3.2.7 Key IFRS metrics
      8. 3.2.8 Tariff Policy
      9. 3.2.9 Investments
      10. 3.2.10 Innovations
      11. 3.2.11 Progress of the Digital Transformation Program

For the operation of the site, we collect cookies, information about the IP address and location of users. If you do not want this data to be processed, please leave the site.

3.2.8 Tariff Policy

Electricity transmission tariffs

Permenergo Index 5 years (2023-2027)
Sverdlovenergo RABregulatory asset base 5 years (2024-2028)
Chelyabenergo Index 5 years (2023-2027)

In 2024, the regulators applied the return on invested capital method (RABregulatory asset base) to Sverdlovenergo and method of long-term indexation of the gross revenue requirement (INDEX) to Permenergo and Chelyabenergo.

Uniform (“pie”) tariffs comprise expenses of all grid companies operating in the region to be annually prescribed for the next year during the long-term regulation period. Pursuant to existing tariff regulation laws, a gross revenue requirement is subject to annual fine-tuning, adjusted for changed real and target calculations, executed investment program and achieved reliability and quality of service indicators. Uniform (“pie”) electricity transmission tariffs to be enforced in 2024 were approved by the tariff decisions of the relevant regional regulators[20-22].

Uniform (“pie”) electricity transmission tariffs for 2024 were set by the regulators within the FASFederal Antimonopoly Service-approved maximum and minimum tariff limits.

PAO Rosseti Ural’s GRRgross revenue requirement composition and its YoYyear on year changes

* Information hereof complies with the 2022-2024 tariff model, used by the regulators in setting of the 2022-2024 tariffs for electricity transmission.

Key factors that changed the “pie” gross revenue requirement in 2024, RUBruble million

Branch 2022 2023 2024 2024/2023, % Explanations on 2024/2023 changes
Permenergo
Electricity transmission GRRgross revenue requirement approved in the tariffs, incl: 23,351 27,225 29,497 108.35% Growth of unified (pie) tariffs
GRRgross revenue requirement for own needs 10,713 13,675 14,427 105.50%
PAOPublic Joint-Stock Company FSK-Rosseti services 3,521 3,835 4,096 106.81% Growth of UNESunited national energy system tariffs
Loss compensation 5,224 4,476 4,771 106.59% Growth of loss purchase price
Payments to RGOsRegional grid operators (in line with the contracts) 3,893 5,239 6,203 118.40% Growth of individual tariffs for RGOsRegional grid operators
Sverdlovenergo
Electricity transmission GRRgross revenue requirement approved in the tariffs, incl: 40,027 48,050 49,312 102.63% Growth of unified (pie) tariffs
GRRgross revenue requirement for own needs 11,923 16,229 16,249 100.12%
PAOPublic Joint-Stock Company FSK-Rosseti services 7,869 9,282 10,545 113.61% Growth of UNESunited national energy system tariffs
Loss compensation 5,189 6,088 4,549 74.72% Revision of loss norms due to the beginning of the second new long-term regulation period
Payments to RGOsRegional grid operators (in line with the contracts) 15,046 16,451 17,969 109.23% Growth of individual tariffs for RGOsRegional grid operators
Chelyabenergo
Electricity transmission GRRgross revenue requirement approved in the tariffs, incl: 24,448 27,204 28,624 105.22% Growth of unified (pie) tariffs
GRRgross revenue requirement for own needs 9,534 10,867 12,336 113.52%
PAOPublic Joint-Stock Company FSK-Rosseti services 3,839 4,420 5,108 115.57% Growth of UNESunited national energy system tariffs
Loss compensation 4,649 5,037 5,713 113.42% Growth of loss purchase price
Payments to RGOsRegional grid operators (in line with the contracts) 6,426 6,880 5,467 79.46% Reduction of the number of RGOsRegional grid operators due to the deprivation of their RGOregional grid operators status as a result of failure to comply with criteria.

Analysis of revisions of the average electricity transmission tariff (adjusted for net supply on generator voltage level), RUBruble/ kWhkilowatt-hour*

Branch 2022 2023 2024
Permenergo 1.522 1.774 1.922
Sverdlovenergo 1.449 1.772 1.853
Chelyabenergo 1.559 1.742 1.834
TOTAL 1.497 1.765 1.866
Growth, % 3.1% 17.9% 5.8%

* Information hereof complies with the 2022-2024 tariff model, used by the regulators in setting of the 2022-2024 tariffs for electricity transmission.

Technological connection fee

Pursuant to the Guidelines[23] the regulators of the Perm, Sverdlovsk and Chelyabinsk regions have set the 2024 standardized tariff rates, privileged connection rates per 1 kW capacity and connection fee formulas. 2024 connection rates are approved by the regional regulators[24-27].

Rates for individuals with maximum 0-15 kW capacity inclusive (incl. previously connected capacity at the point) to be connected to 0-0.4 kV grid facilities, provided that the distance between the boundaries of an applicant’s land plot and nearest grid facilities of required voltage, owned by the gridco to which an applicant submitted its request, does not exceed 300 m in urban areas (cities and small towns) and 500 m in rural areas and microgeneration facilities:

Region Rate amount (incl. VATvalue-added tax)
Perm region Since 01.01.2024 RUBruble 7,000 per kWhkilowatt-hour
Perm region Since 01.07.2024 RUBruble 8,000 per kWhkilowatt-hour
Sverdlovsk region RUBruble 8,000 per kWhkilowatt-hour
Chelyabinsk region RUBruble 6,950 per kWhkilowatt-hour

Besides, the connection fee for underprivileged citizenry (low-income citizens, veterans, disabled people, etc.), provided that the distance between the boundaries of an applicant’s land plot and facilities of 0-0.4 kW voltage, owned by the gridco to which an applicant submitted its request, does not exceed 300 m in urban areas (cities and small towns) and 500 m in rural areas, was set at RUBruble 1,119 / kW, incl. VATvalue-added tax (Perm and Sverdlovsk regions) and RUBruble 1,114.07 / kWhkilowatt-hour, incl. VATvalue-added tax (Chelyabinsk region).

On the whole, increased 2024 average connection cost per maximum capacity unit (“last mile” activities, executed contracts), compared to 2023, was due to increased standardized tariff rates, incl. 1 kWhkilowatt-hour requested capacity, in 2024 (increased cost of connection), as well as reduced connected capacity for applicants requesting 0-150 kW. The primary factor of grown average rate S1 (arrangement and technical activities per one contract) is indexation of its components.

Besides, the regulators approved fees for connection to the Company’s networks under individual project, the cost computed with the use of approved standardized tariff rates pursuant to the guidelines. All in all, there were 25 resolutions on setting individual rates worth RUBruble 1,991 million, net of VATvalue-added tax. Also, RUBruble 908 million planned expenses related to connection, not included into the connection fee, were added into the GRRgross revenue requirement of transmission tariffs.

Download

Indicator MU 2022 2023 2024 2024/2023
Electricity transmission GRRgross revenue requirement approved in the tariffs, incl: RUBruble million 87,826 102,479 107,433 104.83%
GRRgross revenue requirement for own needs RUBruble million 32,170 40,771 43,012 105.50%
Payments to PAOPublic Joint-Stock Company FSK-Rosseti RUBruble million 15,229 17,537 19,749 112.61%
Loss compensation RUBruble million 15,062 15,601 15,033 96.36%
Payments to RGOsRegional grid operators (in line with the contracts) RUBruble million 25,365 28,570 29,639 103.74%
“Pie” net supply kWhkilowatt-hour million 58,660 58,072 57,569 99.13%
Average transmission tariff (breakdown by branches) RUBruble/kWh 1.497 1.765 1.866 105.75%
Standardized tariff rates to cover expenses related to connection of consumers’ equipment, grid facilities owned by gridcos and other entities, in line with clause 16a of the FASFederal Antimonopoly Service Guidelines
Permenergo
For instances, stipulated by para. 6 of clause 24 of the FASFederal Antimonopoly Service Guidelines RUBruble per one connection 8,384.00 9,097.00 9,660.00 106.2%
For instances that are not covered by para. 6 of clause 24 of the FASFederal Antimonopoly Service Guidelines RUBruble per one connection 8,694.00 9,494.00 10,907.00 114.9%
Sverdlovenergo
For instances, stipulated by para. 6 of clause 24 of the FASFederal Antimonopoly Service Guidelines RUBruble per one connection 11,519.00 13,255.00 15,733.00 118.7%
For instances that are not covered by para. 6 of clause 24 of the FASFederal Antimonopoly Service Guidelines RUBruble per one connection 17,843.00 20,715.00 27,867.00 134.5%
Chelyabenergo
For instances, stipulated by para. 6 of clause 24 of the FASFederal Antimonopoly Service Guidelines RUBruble per one connection 13,895.86 14,729.61 15,790.14 107.20%