      1. 3.2.1 Network Exploitation and Grid Asset Consolidation
      2. 3.2.2 Connection
      3. 3.2.3 Electricity Transmission
      4. 3.2.4 Additional (non-tariff) services
      5. 3.2.5 Consumer liaison
      6. 3.2.6 Key RAS metrics
      7. 3.2.7 Key IFRS metrics
      8. 3.2.8 Tariff Policy
      9. 3.2.9 Investments
      10. 3.2.10 Innovations
      11. 3.2.11 Progress of the Digital Transformation Program

For the operation of the site, we collect cookies, information about the IP address and location of users. If you do not want this data to be processed, please leave the site.

3.2.9 Investments

The PAOPublic Joint-Stock Company Rosseti Ural’s investment program for 2024 was adopted by the Ministry of Energy Decree[28].

The Company’s 2022-2024 cost and physical parameters

Parameter 2022 2023 2024 2024/2023, %
Funding, RUBruble million plus VATvalue-added tax 12,602 20,239 19,494 -4%
Capex, RUBruble million net of VATvalue-added tax 8,504 16,089 16,081 0%
New fixed assets, RUBruble million net of VATvalue-added tax 7,298 14,446 16,834 17%
Commissioning of transformer capacity, MVA 264 1,652 832 -50%
Commissioning of power lines, km 1,870 7,605 1,780 -77%

Implementation of the investment program includes handling of the following problems:

Investment funding structure in 2022-2024, RUBruble million, incl. VATvalue-added tax

Indicator 2022 2023 2024 2024/2023, %
Total: 12,602 20,239 19,494 -4%
Connection 7,369 11,475 11,367 -1%
Reconstruction, upgrade and retrofitting 4,166 5,784 5,200 -10%
Investment projects, implemented under energy sector perspective development schemes and programs 370 163 311 91%
Other greenfield construction of energy facilities 136 182 352 94%
Purchase of land plots for investment projects 0 0 0 0%
Other investment projects 561 2,636 2,264 -14%

The bulk of the 2024 funding (58%) was channeled to connection. Investments spent on reconstruction, upgrade and retrofitting totaled 27%. A 12% share of the total funding was spent on other investment projects (ready-to-operate devices, IT projects, etc.), funding of the investment projects, implemented under the energy sector perspective development schemes and programs totaled 2%; funding on greenfield construction totaled 2%. As for the sources of financing, the Company’s internal funds contributed the most to the total funding (89% or RUBruble 17,413 million). Raised funds totaled RUBruble 2,081 million or 11%. We have no state-funded projects.

The largest investment projects completed in 2024

Region Title of an investment project Goals Commissioning in 2024
Perm region Reconstruction of PS 110/6 kV “Severnaya” substation (replacement of 2х16 MVA power transformers for 2х25 MVA ones, 110 kV circuit breakers, RPArelay protection automation devices) (50 MVA, 2 pcs of 110 kV GISgeoinformation system, 1 FOL) Development of the electric grids. Reduction of emergency load of the substation. Execution of the Ministry of Energy Decree[29] RUBruble 394 million
Sverdlovsk region Construction of PS 110 kV “Chekmash” substation and branch lines to PS 110 kV “Chekmash” substation from 110 kV “Arti-Manchazh” aerial power line with branch line to PS “Siminchi” substation (40 MVA; 1.54 km of a 110 kV aerial power line; disconnector (2 pcs), circuit breaker (12 pcs) Development of the electric grids. Execution of a contract on connection RUBruble 498 million
Sverdlovsk region Reconstruction of PS 110/35/6 kV “Pyshma” substation (grid complex of 110/35/6 kV “Pyshma” substation): 120 MVA, 110 kV aerial power line (0.542 km), 110 kV cable power line кВ (0.541 km), 35 kv aerial power line (0.301 km), 35 kV cable power line (0.380 km), 1.142 ha, circuit breakers (36 pcs) Development of the electric grids. Execution of contracts on connection and compensation of expenses agreements. RUBruble 1,228 million
Sverdlovsk region Reconstruction of PS 110 kV “Sverdlovskaya” substation (80 MVA, 110 aerial power line (0.434 km), 110 kV aerial power line (0.135 km), 35 kV aerial power line (0.124 km), 35 kV aerials power line (0.302 km), 10 kV aerial power line (0.225 km), circuit breakers (43 pcs) Development of the electric grids. Execution of the Ministry of Energy Decree[29] RUBruble 939 million
Chelyabinsk region Reconstruction of PS 110 kV “Kremenkul” substation (replacement of the 1st power transformer with capacity upgrade from 10 MVA to 16 MVA, installation of the 2nd power transformer with capacity 16-32 MVA, reconstruction of incoming 110 kV aerial power lines (2х3.8 km), replacement of high-speed grounding switch for 110 kV circuit breakers (3 pcs.), re-arrangement of incoming 10 kV aerial power line by changing installation method (1.273 km) Development of the electric grids. Execution of the contracts on connection. RUBruble 705 million

Long-term investment program

The PAOPublic Joint-Stock Company Rosseti Ural’s investment program for 2024-2028 was adopted by the Ministry of Energy Decree[28].

The Company’s 2025-2028 cost and physical parameters

Parameter 2025 2026 2027 2028
Funding, RUBruble million, incl VATvalue-added tax 17,722 14,424 13,464 10,790
Capex, RUBruble million net of VATvalue-added tax 14,674 11,317 11,120 9,349
New fixed assets, RUBruble million net of VATvalue-added tax 15,604 10,807 11,613 9,957
Commissioning of transformer capacity, MVA 416 113 107 169
Commissioning of power lines, km 1,638 1,172 1,033 844

The Company’s investment program for 2025-2029 stipulates RUBruble 56,400 million (incl. VATvalue-added tax) funding, RUBruble 46,461 million (net of VATvalue-added tax) capex, RUBruble 47,981 million (net of VATvalue-added tax) new fixed assets. The Company’s 2025-2029 investment program is prepared with due allowances to regional development plans, equipment health, importance of grid facilities and current domestic environment.